List of activities, activity duration and dependencies

Task No Task Name Duration Resources Reqd Predecessors Spl Notes
1 Initial Study
2 Study Existing System 4 days An (150%)
3 Carry Out Interviews 2 days An, Ac
4 Prepare Documentation 4 days An (150%), Ad, Printing 2, 3
5 Feasibility Study
6 Identify Problems 4 days An 1
7 Analyse Problems 3 days An (200%) 6
8 Estimate Project Cost 6 days Ac 7
9 Assess Project Risk 4 days An 7
10 Propose Solution 3 days An, Meeting 8, 9
11 Task Scheduling 2 Days An 10
12 Requirements Analysis
13 Investigate Current Environment 7 days Pr (200%) 5
14 Define Requirements 6 days An, Pr (50%) 5
15 Requirements Specification
16 Prepare Specifications 4 days An 12
17 Prepare Case Diagram 6 days Pr 12
18 Prepare Data Dictionary 8 days Pr (150%) 12
19 Prototyping 12 days Pr 18, 16, 17
20 System Design
21 Design New System 4 days An 19
22 Design Test Plan 2 days Pr (150%) 15
23 Coding and Testing
24 Coding 10 days Pr (150%) 21
25 Unit Testing 5 days Pr 24
26 Integration Testing 3 days Pr (200%) 25
27 Update Data Dictionary 1 day Pr (200%), Ad (50%) 24
28 System Testing
29 Hardware Testing 3 days Pr (150%) 23
30 Acceptance Testing 3 days An 29
31 Prepare Documentation 6 days Ac (50%), Ad, Printing 24

Abbreviations: An - Analyst, Ac Accountant, Pr Programmer, Ad Administrative Assistant Mt Meeting, Prn - Printing

Each meeting costs $400 and the printing activity costs $100 per activity. The cost is assigned at the start.

Open the MS Project document "MS Project Assignment 2 Data file". This is a MS Project file with project information such as duration, precedence requirements etc., already entered in this file. Your assignment requires you to do the following in MS Project:

1. Create the list of resources available for completing the project (please review the MS Project videos on this before you start). We have two programmers, two analysts, one accountant and one administrative assistant. Please add your first name as accountant while declaring resources. Also add "Meeting" and Printing as cost resources. Please add the resources in the appropriate resources section of MS Project. Please remember that all these resources are Work resources except for meeting. Programmers earn $100/hr and $150 per hour for overtime, analysts and accountants earn $85/hr and $150 per hour for overtime, and administrative assistant earns $50/hr and $75 per hour for overtime.

2. Assign resources required for each activity based on the table in previous page (this is the Resources Reqd column). Please remember while allocating resources your first name should be used as accountant.

3. Please add a new column in your MS Project file to show each activity cost and total project cost.

When you complete the work above, you will see some activities are marked to indicate over allocated resources (i.e., you do not have resources to complete the task as planned). Please create a Word document and list the activities that show over allocation of resources in the following format

Task No Task Name Name of over allocated resource(s)

Academic Honesty!
It is not our intention to break the school's academic policy. Posted solutions are meant to be used as a reference and should not be submitted as is. We are not held liable for any misuse of the solutions. Please see the frequently asked questions page for further questions and inquiries.
Kindly complete the form. Please provide a valid email address and we will get back to you within 24 hours. Payment is through PayPal, Buy me a Coffee or Cryptocurrency. We are a nonprofit organization however we need funds to keep this organization operating and to be able to complete our research and development projects.